  1. Q26 · Mechanical Engineering

    The preparatory functions in Computer Numerical Controlled (CNC) machine programing are denoted by the alphabet
    • A.G
    • B.M
    • C.P
    • D.O
    Show answer / उत्तर देखें

    Answer: A G

    Official GATE 2024 answer key: (A).
  2. Q27 · Mechanical Engineering

    A queueing system has one single server workstation that admits an infinitely long queue. The rate of arrival of jobs to the queueing system follows the Poisson distribution with a mean of 5 jobs/hour. The service time of the server is exponentially distributed with a mean of 6 minutes. In steady state operation of the queueing system, the probability that the server is not busy at any point in time is
    • A.0.20
    • B.0.17
    • C.0.50
    • D.0.83
    Show answer / उत्तर देखें

    Answer: C 0.50

    Official GATE 2024 answer key: (C).
  3. Q28 · Mechanical Engineering

    The matrix [1 𝑎 8 3] (where 𝑎 > 0) has a negative eigenvalue if 𝑎 is greater than
    • A.3 8
    • B.1 8
    • C.1 4
    • D.1 5
    Show answer / उत्तर देखें

    Answer: A 3 8

    Official GATE 2024 answer key: (A).
  4. Q29 · Mechanical Engineering

    A company orders gears in conditions identical to those considered in the economic order quantity (EOQ) model in inventory control. The annual demand is 8000 gears, the cost per order is 300 rupees, and the holding cost is 12 rupees per month per gear. The company uses an order size that is 25% more than the optimal order quantity determined by the EOQ model. The percentage change in the total cost of ordering and holding inventory from that associated with the optimal order quantity is
    • A.2.5
    • B.5
    • C.0
    • D.12.5
    Show answer / उत्तर देखें

    Answer: A 2.5

    Official GATE 2024 answer key: (A).
  5. Q30 · Mechanical Engineering

    At the current basic feasible solution (bfs) 𝒗𝟎 (𝒗𝟎 ∈ ℝ5), the simplex method yields the following form of a linear programming problem in standard form. 𝑚𝑖𝑛𝑖𝑚𝑖𝑧𝑒 𝑧 = −𝑥1 − 2𝑥2 𝑠. 𝑡. 𝑥3 = 2 + 2𝑥1 − 𝑥2 𝑥4 = 7 + 𝑥1 − 2𝑥2 𝑥5 = 3 − 𝑥1 𝑥1, 𝑥2, 𝑥3, 𝑥4, 𝑥5 ≥ 0 Here the objective function is written as a function of the non-basic variables. If the simplex method moves to the adjacent bfs 𝒗𝟏 (𝒗𝟏 ∈ ℝ5) that best improves the objective function, which of the following represents the objective function at 𝒗𝟏, assuming that the objective function is written in the same manner as above?
    • A.𝑧 = −4 − 5𝑥1 + 2𝑥3
    • B.𝑧 = −3 + 𝑥5 − 2𝑥2
    • C.𝑧 = −4 − 5𝑥1 + 2𝑥4
    • D.𝑧 = −6 − 5𝑥1 + 2𝑥3
    Show answer / उत्तर देखें

    Answer: A 𝑧 = −4 − 5𝑥1 + 2𝑥3

    Official GATE 2024 answer key: (A).